(ATT south of NC 54 and bridge spanning I-40)

Durham’s Public Works Department web site has reinstated their posting of summaries of the project’s status. The final permits have now been obtained and the Request for Proposals were released in early June. Opening of the formal, sealed bids is now scheduled for July 13th and a contract should be signed by early Fall. Construction is expected to require 1 year.